0) sampleTaskPlan_20090707_c | 1/6 8:00 AM | 4/28 11:29 AM | < 642h | | |
1) ACME Corporation Website | 1/6 8:00 AM | 4/28 11:29 AM | < 642h | | |
1.1) Project Manager Allocation | 1/6 9:30 AM | 4/15 1:55 PM | < 571.5h | | Project Manager {35% of 100%} |
1.2) Discovery | 1/6 8:00 AM | 1/8 6:30 PM | 24h | | |
1.2.1) Product Requirements Definition | 1/6 8:00 AM | 1/8 6:30 PM | 24h | | |
1.2.1.1) Client Input/Guidelines On PRD Due | 1/6 8:00 AM | 1/6 8:00 AM | | | ACME Corporation |
1.2.1.2) PRD Generation | 1/6 9:30 AM | 1/6 6:30 PM | 8h | 1.2.1.1 | Project Director; Producer |
1.2.1.3) PRD Submission to Client | 1/6 6:30 PM | 1/6 6:30 PM | | 1.2.1.2 | Almer/Blank |
1.2.1.4) PRD Feedback from Client | 1/8 6:30 PM | 1/8 6:30 PM | | 1.2.1.3+16h | ACME Corporation |
1.2.1.5) PRD Rework | 1/7 9:30 AM | 1/7 2:30 PM | 4h | | Project Director; Producer |
1.2.1.6) PRD Resubmission to Client | 1/7 2:30 PM | 1/7 2:30 PM | | 1.2.1.5 | Almer/Blank |
1.2.1.7) PRD Initial Sign-Off from Client | 1/8 2:30 PM | 1/8 2:30 PM | | 1.2.1.6+8h | ACME Corporation |
1.2.1.8) Project Guide Documentation Update | 1/8 2:30 PM | 1/8 3:30 PM | 1h | 1.2.1.7 | Project Director |
1.3) Design | 1/8 6:30 PM | 3/17 6:02 PM | > 383.5h | 1.2.1 | |
1.3.1) Information Design | 1/8 6:30 PM | 1/22 5:18 PM | > 78.75h | | |
1.3.1.1) Client Input/Guidelines On Information Design Due | 1/8 6:30 PM | 1/8 6:30 PM | | | ACME Corporation |
1.3.1.2) Information Design Document Creation | 1/11 9:30 AM | 1/13 1:42 PM | < 19.25h | 1.3.1.1 | Project Director; Producer {25% of 100%} |
1.3.1.3) Information Design Document Submitted to Client | 1/13 1:42 PM | 1/13 1:42 PM | | 1.3.1.2 | Almer/Blank |
1.3.1.4) Information Design Document Feedback from Client | 1/19 1:42 PM | 1/19 1:42 PM | | 1.3.1.3+32h | ACME Corporation |
1.3.1.5) Information Design Rework | 1/19 1:42 PM | 1/20 3:18 PM | > 9.5h | 1.3.1.4 | Project Director; Producer {25% of 100%} |
1.3.1.6) Information Design Resubmission to Client | 1/20 3:18 PM | 1/20 3:18 PM | | 1.3.1.5 | Almer/Blank |
1.3.1.7) Information Design Draft Approval from Client | 1/22 3:18 PM | 1/22 3:18 PM | | 1.3.1.6+16h | ACME Corporation |
1.3.1.8) Project Guide Documentation Update | 1/22 3:18 PM | 1/22 5:18 PM | 2h | 1.3.1.7 | Project Director |
1.3.2) Interaction Design | 1/22 5:18 PM | 2/15 4:09 PM | > 126.75h | 1.3.1 | |
1.3.2.1) Client Input/Guidelines On Interaction Design Due | 1/22 5:18 PM | 1/22 5:18 PM | | | ACME Corporation |
1.3.2.2) Interaction Design Document Creation | 1/22 5:18 PM | 2/1 11:09 AM | > 42.75h | 1.3.2.1 | UX Designer; Project Director {40% of 100%} |
1.3.2.3) Interaction Design Document Submitted to Client | 2/1 11:09 AM | 2/1 11:09 AM | | 1.3.2.2 | Almer/Blank |
1.3.2.4) Interaction Design Document Feedback from Client | 2/8 11:09 AM | 2/8 11:09 AM | | 1.3.2.3+40h | ACME Corporation |
1.3.2.5) Information Design Document Re-work | 2/8 11:09 AM | 2/11 11:09 AM | 24h | 1.3.2.4 | UX Designer |
1.3.2.6) Information Design Document Redelivery to Client | 2/11 11:09 AM | 2/11 11:09 AM | | 1.3.2.5 | Almer/Blank |
1.3.2.7) Information Design Document Draft Approval from Client | 2/15 11:09 AM | 2/15 11:09 AM | | 1.3.2.6+16h | ACME Corporation |
1.3.2.8) Project Guide Documentation Update | 2/15 11:09 AM | 2/15 4:09 PM | 4h | 1.3.2.7 | Project Director |
1.3.3) Visual Design | 2/15 4:09 PM | 3/12 6:02 PM | < 154h | 1.3.2 | |
1.3.3.1) Client Input/Guidelines On Visual Design Due | 2/15 4:09 PM | 2/15 4:09 PM | | | ACME Corporation |
1.3.3.2) Moodboard Creation | 2/15 4:09 PM | 2/17 2:04 PM | < 14h | 1.3.3.1 | Producer {15% of 100%}; Visual Designer |
1.3.3.3) Moodboard Delivery | 2/17 2:04 PM | 2/17 2:04 PM | | 1.3.3.2 | Almer/Blank |
1.3.3.4) Moodboard Selection/Feedback | 2/17 2:04 PM | 2/17 2:04 PM | | 1.3.3.3 | ACME Corporation |
1.3.3.5) Visual Design Creation | 2/17 2:04 PM | 2/27 3:00 PM | < 60.5h | 1.3.3.4 | Producer {15% of 100%}; Visual Designer |
1.3.3.6) Visual Design Submitted to Client | 2/27 3:00 PM | 2/27 3:00 PM | | 1.3.3.5 | Almer/Blank |
1.3.3.7) Visual Design Feedback from Client | 3/5 6:30 PM | 3/5 6:30 PM | | 1.3.3.6+40h | ACME Corporation |
1.3.3.8) Visual Design Re-work | 3/6 9:30 AM | 3/10 3:22 PM | > 20.75h | 1.3.3.7 | Producer {15% of 100%}; Visual Designer |
1.3.3.9) Visual Design Redelivery to Client | 3/10 3:22 PM | 3/10 3:22 PM | | 1.3.3.8 | Almer/Blank |
1.3.3.10) Visual Design Draft Approval from Client | 3/12 3:22 PM | 3/12 3:22 PM | | 1.3.3.9+16h | ACME Corporation |
1.3.3.11) Project Guide Documentation Update | 3/12 3:22 PM | 3/12 6:02 PM | < 2.75h | 1.3.3.10 | Project Director; Producer {50% of 100%} |
1.3.4) Final Design Documentation to Client | 3/12 6:02 PM | 3/12 6:02 PM | | 1.3.1, 1.3.2, 1.3.3 | Almer/Blank |
1.3.5) Final Design Deliverables Sign-Off from Client | 3/17 6:02 PM | 3/17 6:02 PM | | 1.3.4+24h | ACME Corporation |
1.4) Software Design | 2/15 4:09 PM | 3/11 11:09 AM | 140h | 1.3.2 | |
1.4.1) Client Input/Guidelines On Software Design Due | 2/15 4:09 PM | 2/15 4:09 PM | | | ACME Corporation |
1.4.2) Software Design | 2/15 4:09 PM | 3/4 11:09 AM | 100h | | Software Architect |
1.4.3) Software Design Submitted to Client | 2/15 4:09 PM | 2/15 4:09 PM | | | Almer/Blank |
1.4.4) Software Design Feedback from Client | 2/19 4:09 PM | 2/19 4:09 PM | | 1.4.3+32h | ACME Corporation |
1.4.5) Software Design Re-work | 3/4 11:09 AM | 3/9 11:09 AM | 24h | 1.4.4 | |
1.4.5.1) Software Architecture Re-work | 3/4 11:09 AM | 3/9 11:09 AM | 24h | | Software Architect |
1.4.6) Software Design Redelivery to Client | 3/9 11:09 AM | 3/9 11:09 AM | | 1.4.5 | Almer/Blank |
1.4.7) Software Design Draft Approval from Client | 3/11 11:09 AM | 3/11 11:09 AM | | 1.4.6+16h | ACME Corporation |
1.5) Engineering | 3/11 11:09 AM | 4/28 11:29 AM | > 272.25h | 1.4 | |
1.5.1) Beta Assets Received from Client | 3/11 11:09 AM | 3/11 11:09 AM | | 1.5.2SS | ACME Corporation |
1.5.2) Beta | 3/11 11:09 AM | 4/5 4:09 PM | 140h | | |
1.5.2.1) Beta Test Plan Generation | 3/12 6:02 PM | 3/16 2:02 PM | 12h | | Project Director |
1.5.2.2) Engineering | 3/11 11:09 AM | 3/29 4:09 PM | 100h | | Developer |
1.5.2.3) Internal Beta QA | 3/16 2:02 PM | 3/19 2:02 PM | 24h | 1.5.2.1 | QA |
1.5.2.4) Beta Engineering Re-work from Internal QA | 3/29 4:09 PM | 4/5 4:09 PM | 40h | 1.5.2.3 | Developer |
1.5.2.5) Beta Launch | 3/19 2:02 PM | 4/2 4:29 PM | < 82.5h | 1.5.2.3 | |
1.5.2.5.1) Initial Beta Delivery | 3/19 2:02 PM | 3/19 2:02 PM | | | Almer/Blank |
1.5.2.5.2) Client Feedback on Beta | 3/26 2:02 PM | 3/26 2:02 PM | | 1.5.2.5.1+40h | ACME Corporation |
1.5.2.5.3) Beta Re-engineering | 4/1 11:09 AM | 4/2 11:09 AM | 8h | 1.5.2.5.2 | Software Architect; Developer |
1.5.2.5.4) Beta Re-delivery | 4/2 11:09 AM | 4/2 11:09 AM | | 1.5.2.5.3 | Almer/Blank |
1.5.2.5.5) Client Approval of Beta | 3/19 2:02 PM | 3/19 2:02 PM | | | ACME Corporation |
1.5.2.5.6) Beta Push | 4/1 5:29 PM | 4/2 4:29 PM | 7h | | Software Architect; Developer |
1.5.2.5.7) Beta Completion | 3/19 2:02 PM | 3/19 2:02 PM | | | Almer/Blank |
1.5.3) Lump Feedback on Beta Due from Client | 4/9 4:29 PM | 4/9 4:29 PM | | 1.5.2.5+40h | ACME Corporation |
1.5.4) Final Release Assets Received from Client | 4/9 4:29 PM | 4/9 4:29 PM | | 1.5.5SS | ACME Corporation |
1.5.5) Final Release | 4/9 4:29 PM | 4/28 11:29 AM | 100h | 1.5.3 | |
1.5.5.1) Final Release Test Plan Generation | 4/9 4:29 PM | 4/13 11:29 AM | 12h | | Project Director |
1.5.5.2) Engineering | 4/9 4:29 PM | 4/21 11:29 AM | 60h | | Developer |
1.5.5.3) Internal Final Release QA | 4/13 11:29 AM | 4/19 11:29 AM | 32h | 1.5.5.1 | QA |
1.5.5.4) Final Release Engineering Re-work | 4/21 11:29 AM | 4/27 11:29 AM | 32h | 1.5.5.3 | Developer |
1.5.5.5) Final Delivery | 4/27 11:29 AM | 4/28 11:29 AM | 8h | 1.5.5.4 | |
1.5.5.5.1) Client Approval of Delivery | 4/27 11:29 AM | 4/27 11:29 AM | | | ACME Corporation |
1.5.5.5.2) Push | 4/27 11:29 AM | 4/28 11:29 AM | 8h | | Software Architect; Developer |
1.5.5.5.3) Project Completion | 4/27 11:29 AM | 4/27 11:29 AM | | | Almer/Blank |